Work has finished on the Chlorination Building tie-in and water will gradually be turned on starting in Marystown North and the housing area on down to Creston North. From there, water will be restored in Creston South on down to Little Bay and finally Mooring Cove. Fire hydrants will be bled to remove air from the lines.
Residents are reminded that a boil order is in effect until further notice.
The Town would like to thank everyone who worked on this project yesterday and today, especially given the colder temperatures.
The Town would also like to thank our Fire Department that was on standby for any emergency.
Lastly, the Town would like to thank all residents and businesses for their patience during the shutdown and extended delay.